Title: BMM2002-10 - Measuring the Impacts of the Delivery System on Project Performance -- Design-Build and Design-Bid-B
Publication Date: 11/1/2002
Product Type: Benchmarking Report
Status: Tool
Pages: 97
Documents the impacts of the project delivery system on project outcomes and provides a means by which the economic value of the design-build (DB) and the design-bid-build (DBB) project delivery systems may be evaluated. Sponsored by NIST.
Order Now  

Abstract

This study, sponsored by the National Institute for Standards and Technology (NIST), was designed to meet two objectives: to produce a comprehensive information set that documents the impacts of the project delivery system on project outcomes, and to provide the construction industry a means by which it may measure and evaluate the economic value of the design-build and the design-bid-build project delivery systems.

The study consisted of four tasks. The first was a statistical analysis of a broad crosssection of projects from the Construction Industry InstituteTM (CIITM) Benchmarking and Metrics (BM&M) database. The second was to tabulate key database characteristics and important findings from the Task 1 statistical analysis. Task 3 was the statistical analysis and tabulation of four subsets of projects from the CII database: by sector, industry group, cost category, and project nature. The fourth task was the preparation and delivery of this technical report, which synthesizes the findings from Tasks 1-3 of this research effort.

The analytic data set comprises all U.S. domestic and international projects submitted by owners and contractors between 1997 and 2000 using versions 2.0 through 6.0 of the CII Benchmarking and Metrics questionnaire. Using information reported on the BM&M questionnaire, both owner and contractor-submitted projects were classified as either design-build (DB) or design-bid-build (DBB) projects. The results were presented for both owner and contractors in tables that compared DB and DBB projects overall and by each of the four subsets of projects.

The results of this study show that on average DB projects were about four times larger than DBB projects in terms of project cost. Public sector projects made less use of the DB project delivery system than private sector projects. Industrial projects made greater use of DB than did building projects. Overall, owner-submitted DB projects outperformed DBB projects in cost, schedule, changes, rework, and practice use, although statistically significant differences were found only for schedule, changes, rework, and practice use. Contractor-submitted DB projects overall outperformed DBB projects in changes, rework, and practice use, but the difference was statistically significant only for change performance. Contractor-submitted DBB projects overall outperformed DB projects in schedule, and the difference was statistically significant. Pre-project planning and project change management practice use had the greatest impacts on cost performance for owner-submitted DB and DBB projects. Team building practice use had the greatest schedule performance impact on owner-submitted DB projects. Project change management and team building practice use had the greatest impacts on contractor-submitted DB project performance. Project change management occurred most frequently as the practice that had the greatest performance impact among contractor-submitted DBB projects.


Abstract

This study, sponsored by the National Institute for Standards and Technology (NIST), was designed to meet two objectives: to produce a comprehensive information set that documents the impacts of the project delivery system on project outcomes, and to provide the construction industry a means by which it may measure and evaluate the economic value of the design-build and the design-bid-build project delivery systems.

The study consisted of four tasks. The first was a statistical analysis of a broad crosssection of projects from the Construction Industry InstituteTM (CIITM) Benchmarking and Metrics (BM&M) database. The second was to tabulate key database characteristics and important findings from the Task 1 statistical analysis. Task 3 was the statistical analysis and tabulation of four subsets of projects from the CII database: by sector, industry group, cost category, and project nature. The fourth task was the preparation and delivery of this technical report, which synthesizes the findings from Tasks 1-3 of this research effort.

The analytic data set comprises all U.S. domestic and international projects submitted by owners and contractors between 1997 and 2000 using versions 2.0 through 6.0 of the CII Benchmarking and Metrics questionnaire. Using information reported on the BM&M questionnaire, both owner and contractor-submitted projects were classified as either design-build (DB) or design-bid-build (DBB) projects. The results were presented for both owner and contractors in tables that compared DB and DBB projects overall and by each of the four subsets of projects.

The results of this study show that on average DB projects were about four times larger than DBB projects in terms of project cost. Public sector projects made less use of the DB project delivery system than private sector projects. Industrial projects made greater use of DB than did building projects. Overall, owner-submitted DB projects outperformed DBB projects in cost, schedule, changes, rework, and practice use, although statistically significant differences were found only for schedule, changes, rework, and practice use. Contractor-submitted DB projects overall outperformed DBB projects in changes, rework, and practice use, but the difference was statistically significant only for change performance. Contractor-submitted DBB projects overall outperformed DB projects in schedule, and the difference was statistically significant. Pre-project planning and project change management practice use had the greatest impacts on cost performance for owner-submitted DB and DBB projects. Team building practice use had the greatest schedule performance impact on owner-submitted DB projects. Project change management and team building practice use had the greatest impacts on contractor-submitted DB project performance. Project change management occurred most frequently as the practice that had the greatest performance impact among contractor-submitted DBB projects.